INTER-ARRAY CABLE · OFFSHORE WIND
Ready
1
Topology
›
2
Cable Sizing
›
3
Elec. Losses
›
4
Availability
›
5
CAPEX
›
6
Scenarios
›
7
Export
Topology Stats
WTGs0
OSS0
Strings—
Crossings—
Total Length—
Wind Turbine (WTG)
Offshore Substation
Inter-Array Cable

Cable Schedule — Per Segment

StringSeg.WTGs UpstreamI calc (A)Ampacity (A)CSA (mm²)Length (m)MarginStatus
Run WS1 topology optimiser first, then size cables.

Summary by CSA Section

CSA (mm²)ConductorSegmentsTotal Length (m)Total Length (km)Share (%)

Loss Breakdown by String

StringLength (km)Joule Loss (kW)Diel. Loss (kW)Total (kW)% AEP
Complete WS2 first.

Loss Sensitivity (P10 / P50 / P90 / 100%)

ScenarioLoad (%)Joule (kW)Dielectric (kW)Total (MW)
IAC Electrical Losses vs. Power Output Level (0 → 100% Rated)

Availability Impact per String

StringLength (km)WTGsFR (f/yr)Avg WTGs LostE Loss (MWh/yr)Loss (€/yr)
Complete WS3 first.

Radial vs. Looped Topology — N-1 Comparison

Run availability calculation to see comparison.

CAPEX Breakdown by Component

Cost ComponentBasisAmount (k€)% Total

Cost Distribution

Scenario Comparison Table

Save at least two scenarios, then click "Update Comparison".

Pareto Analysis — CAPEX vs. Availability Loss

Trade-off: Capital Cost (M€) vs Availability Loss (MWh/yr)

Executive Summary

Complete WS1–WS5 to generate the executive summary.

Node Coordinate Export